Develop controls is the first action in which step of the Risk Management process?

Prepare for the Aviation Maintenance Training Center Exam. Study with flashcards and practice questions, complete with hints and explanations. Ace your exam with confidence!

Multiple Choice

Develop controls is the first action in which step of the Risk Management process?

Explanation:
In risk management, after hazards are identified and risk is assessed, the next phase focuses on reducing those risks. The first action in this phase is to develop controls and make risk decisions. This means you design and select specific measures to lower the risk (such as engineering controls, administrative procedures, or PPE) and decide whether the remaining risk is acceptable or if further action is needed (accept, avoid, transfer, or mitigate). Only after these controls are developed and a risk decision is made do you move on to actually implementing the chosen controls. That’s why this option is the correct one.

In risk management, after hazards are identified and risk is assessed, the next phase focuses on reducing those risks. The first action in this phase is to develop controls and make risk decisions. This means you design and select specific measures to lower the risk (such as engineering controls, administrative procedures, or PPE) and decide whether the remaining risk is acceptable or if further action is needed (accept, avoid, transfer, or mitigate). Only after these controls are developed and a risk decision is made do you move on to actually implementing the chosen controls. That’s why this option is the correct one.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy